Minggu, 12 Februari 2012

Pipeline Installation Engineering


Pipeline installation adalah proses pemasangan pipeline di laut. Hal yang harus diperhatikan adalah besarnya stress yang terjadi pada pipe pada saat proses tersebut. Mulai dari saat pipa masih diatas barge, di stinger, dan saat pipa menyentuh seabed. Ada 2 kategori area yang harus dicek, yaitu Overbend dan sagbend. Overbend area dimulai dari pipe masih di atas barge sampe stinger (kecuali roller terakhir pada stinger). Sedangkan sagbend mulai dari roller terakhir pada stinger sampai seabed. Accetance criteria untuk area ini pun berbeda. Menurut DnV OS F101 ‘Submarine Pipeline System’ Section 13, part H300 ‘Simplified Laying Criteria’, disebutkan bahwa utk overbend area menggunakan strain based criteria, sedangkan sagbend menggunakan stress based criteria. Dimana untuk calculated strain maksimal uyang diijinkan adalah 0,205% (Material X52, Static Condition) dan stress maksimal yang diijinkan adalah 87% dari SMYS (Static Condition). Untuk kondisi dynamic analysis maka batasan maksimalnya akan berubah.
Sebenarnya apa perbedaan analysa statis dan analisa dinamis pada instalasi pipeline dengan OFFPIPE? Simpel saja, pada analisa statis asumsinya tidak ada pergerakan dari bargenya (barge dianggap diam/statis) sedangkan pada analisa dinamis kita memasukkan fungsi pergerakan barge. Jadi bargenya kita anggap bergerak karena adanya pengaruh gelombang laut. Oleh karena itu, untuk analisa dinamis kita memerlukan data tambahan berupa data RAO (Response Amplitude Operator) dari barge atau yang biasa dikenal sebagai motion study of the barge dan data lingkungan (gelombang dan arus laut). Data RAO dapat diperoleh salah satunya dari simulasi dengan menggunakan software MOSES.
Untuk project instalasi pipeline ini ada beberapa case yang bias disimulasikan dengan menggunakan OFFPIPE, antara lain:
  • Start-Up Analysis
Analisa pada saat pertama kali pipa akan diluncurkan. Pipa dilas di atas barge lalu ditarik sampai di ujung stinger. Karena pipa tidak bisa bergerak sendiri maka kita perlu menariknya dengan AHT atau winch machine. Setelah pipa berada di ujung stinger, kita kaitkan kabel yang sebelumnya telah diikatkan di DMA (Dead Man Anchor) di dasar laut ke ujung pipa (pipe head). Lalu barge bergerak maju dan proses penyambungan pipa tetap dilakukan sehingga dengan sendirinya pipa tersebut akan turun dan meluncur ke laut dengan dipegangin kabel didepannya. Proses start-up selesai setelah pipe head dan beberapa meter bagian pipa telah berada di dasar laut. Kita bisa membuat simulasi pipa yang ujungnya diikatkan cable yang terhubung di DMA yang ada di dasar laut. Pada beberapa kondisi, kita bisa mengganti DMA dengan kaki jacket. Jadi kabelnya kita kaitkan pada kaki jacket jika kita tidak menggunakan DMA. Simulasi di OFFPIPE dilakukan dengan merubah-rubah panjang pipa dari pendek misal 70meter kemudian dtambah per case 10 meteran sehingga kita akan mendapatkan variasi case panjang pipa pada simulasi OFFPIPE, danakan diperoleh kesan bahwa pipe bergerak dari barge menuju dasar laut. Dalam setiap perubahan itu kita cek strain dan stress yang terjadi dan kita analisa.
  • Normal Laying Analysis
Analisa normal, yaitu asumsinya kondisi saat pipa sudah menyentuh seabed jadi kita tidak lagi menggunakan cable. Yang ada hanya pipa aja. Seperti biasa kita cek strain dan stress yang terjadi dan kita analisa.
  • Abandon Analysis
Abandon adalah keadaan dimana tidak memungkin dilanjutkannya pekerjaan instalasi pipeline karena mungkin cuaca buruk. Untuk itu pekerjaan harus dihentikan dan bagian terakhir pipa yang ada di atas barge harus diturunkan ke dasar laut. Hal ini biasa disebut abandon analysis. Prinsipnya hamper sama sepeti Start-Up analysis, kita menggunakan cable. Tapi untuk case ini kabel posisinya berada di belakang pipa. Jadi simulasi yang dilakukan dengan merubah0rubah panjang pipa mulai pendek sampai panjang. Sehingga diperoleh kesan pipa meluncur ke dasar laur dengan dipegangin cable di belakangnya.
  • Recovery Analysis
  • Laydown Analysis

Evaluation Of Marine Pipeline On-Bottom Stability


On-Bottom Stability Without Significant Hydrodynamic Forcing
The seabed is the pipeline's resting place, literally speaking. The pipeline can be laying on the surface of the seabed or buried in the seabed, or it may be lying on the seabed surface covered with non-local material (rocks, grout bags, etc.). But the seabed is not a hard surface so the pipeline will not necessarily stay where it is initially positioned even when there is no hydrodynamic forcing present. The pipeline may sink into the soft if the downward force exceeds the beating capacity of the bed and may move laterally by sliding if the pipe is installed on a non-horizontal seabed. The movement of the pipeline by seabed failure (slips and slides) is not considered here.
Another hazard for pipelines placed in trenches and covered with backfill material is that they may "float" up through the backfill. The processes responsible for flotation of pipelines have been studied for many years but recently new advances are being made in understanding some of the mechanisms leading to flotation, namely static liquefaction and upheaval buckling. Both these processes are potentially more important now that the pipes are becoming lighter and the hotter products can lead to greater thermal gradients and mechanical stresses.
Subsea developments require the installation of (flexible) pipelines to connect the wellhead to the distribution system and this installation is undertaken by surface vessels ,with diver support or by diverless ROV (Remote Operated Vehicle) technology. In these situations, pipelines are often pulled along the seabed or dragged sideways. Ensuring reliable connection operations requires an adequate knowledge of the seabed soils and configuration of the system being installed. This will help provide accurate predictions of the pulling forces required. Recent advances in the scaling of laboratory scale experiments within the framework of soil mechanics has produced a better understanding of the processes acting and generated better predictions of the loads required to move pipelines over the seabed.

Sumber: http://findarticles.com/p/articles/mi_m3251/is_4_226/ai_n25027356/

Offshore Pipelaying


S-lay Method by Conventionally Moored Lay Barges

The traditional method for installing offshore pipelines in relatively shallow water is commonly referred to as the S-Lay method because the profile of the pipe as it moves in a horizontal plane from the welding and inspection stations on the lay barge across the stern of the lay barge and onto the ocean floor forms an elongated "S." As the pipeline moves across the stern of the lay barge and before it reaches the ocean floor, the pipe is supported by a truss-like circular structure equipped with rollers and known as a stinger. The purpose of the stinger in the S-lay configuration is to control the deflection of the pipe in the over-bend region above the pipeline inflection point in order to return the angle of the pipeline at the surface to the horizontal. The curvature radius of the stinger corresponds to at least the maximum bending stress. To avoid a bending moment peak at the last roller, the pipe must lift off smoothly from the stinger well ahead of the lower end of the stinger.
In extremely deep water the angle of the pipe becomes so steep that the required stinger length may not be feasible. Deeper water depths will result in a steeper lift-off angle of the suspended pipe span at the stinger tip. This will require the stinger to be longer and/or more curved to accommodate the greater arc of reverse curvature in the overbend region. Accordingly, greater stinger buoyancy and/or structural strength will be necessary to support the increased weight of the suspended pipe span.
The practical water depth limit for a large, conventionally moored lay barge that uses the S-lay method is about 1,000 ft, based on a ratio of anchor line length to water depth of about five to one. Therefore, construction of pipelines by conventionally moored lay barges, if used in conjunction with the development of deepwater oil or gas discoveries in the Gulf of Mexico, will probably be limited to those portions of the pipeline routes located in water depths less than 1,000 ft. The term "conventionally moored" means that the location or position of the installation vessel (lay barge) is maintained through anchors, associated anchor chains, and/or cables.
Smaller lay barges, in the 400 ft long by 100 ft wide size range, typically require eight anchors each weighing 30,000 lbs, and a larger barge operating in 1,000 ft of water typically requires 12 anchors (3 anchors per quarter), each weighing 50,000 lbs or more.
In general, the larger the vessel, that is, the greater the target area presented to wind, wave, and current forces, and the heavier the vessel, the higher the holding requirements will be for the mooring system. The rated holding capacity of an anchor system is a function of the weight and size of the anchor and the tensile strength of the chain or cable that secures the anchor to the vessel. An important factor to be considered when there is a choice to be made between a conventionally moored lay barge and a lay barge that uses other means, such as dynamic positioning, to remain on station is the matter of handling the anchors. To deploy and recover the anchors of a lay barge operating in 1,000 ft of water, two anchor-handling vessels with a horsepower rating of 8,000-10,000 each would be required, and there is a shortage of such vessels. On the other hand, a smaller lay barge operating in shallower water requires only one 3,000-5,000 hp anchor-handling vessel.
The number of anchor relocations per mile of offshore pipeline constructed will be dependent upon the size of the lay barge, the water depth, ocean floor conditions in the vicinity of the pipeline installation, and the amount of anchor line that can be stored, deployed, and retrieved by the lay barge. Assuming a lay barge is operating in 1,000 ft of water and is following the accepted practice of deploying an amount of anchor line equal to five times the water depth, the anchors would have to be relocated after each 2,000 ft of pipeline installed.
Minerals Management Service regulations at 30 CFR 250.1003(a)(1) require, with some exceptions, that pipelines installed in water depths of less than 200 ft be buried to a depth of at least 3 ft. The purpose of this requirement is to protect the pipeline from the external damage that could result from anchors and fishing gear, and to minimize interference with the operations of other users of the OCS. For deepwater pipelines, burial issues are a possible concern only for those pipelines that terminate onshore or at shallow-water host facilities.
The burial of a pipeline is carried out during the construction process and is usually accomplished by either a plow or a jet sled towed along the seafloor by the lay barge. Whether a plow or jet sled is used, the distance of the device from the lay barge is adjusted to position the plow or jet sled just ahead of the point where the pipe contacts the seafloor (the touchdown point). Through the action of high-pressure water jets, a jet sled creates a trench in the seafloor into which the pipeline settles. The jet sled, which generally creates more temporary turbidity in the water column than a plowing device, has an operational advantage over a plow. The area of seafloor disturbed by the pipeline burial process is typically just slightly wider than the outside diameter of the pipeline, for example, a trench approximately 15 inches wide by 3 ft deep for a 12-inch pipeline.

S-Lay Method by Dynamically Positioned Lay Barges

The term "dynamically positioned" means that the location or position of the lay barge is maintained by the vessel's very specialized propulsion and station-keeping system which, instead of or in addition to the conventional propeller-rudder system at the stern, employs a system of hullmounted thrusters near the bow, at midship, and at the stern. When in the station-keeping mode, these thrusters, which have the capability to rotate 360o in a horizontal plane, are controlled by a shipboard computer system that usually interfaces with a satellite-based geographic positioning system.
Dynamically positioned lay barges can be used in water depths as shallow as 100 ft, but generally they are not used in water less than 200 ft deep, depending upon pipe size, the nature of the job, and the location. Dynamically positioned lay barges outfitted with the equipment necessary to install reel pipe are sometimes used in shallow water.
The impact on air quality is one of the most significant differences between using a dynamically positioned lay barge and a conventionally moored lay barge to construct a pipeline. In the case of a conventionally moored vessel, the hydrocarbon-fuel-consuming prime movers that drive the propulsion system are typically shut down or operating at minimum speed, fuel consumption, and pollutant emission levels while the vessel is not under way, that is, while the vessel is engaged in pipeline installation activity. The probable requirement for tug assistance to move from station to station during an installation project and the requirement for the services of anchor-handling vessels to deploy, retrieve, and re-deploy anchors contribute to the pollutant emission levels. Contrast this to a dynamically positioned lay barge which, in order to remain on station during a pipeline installation, must constantly operate its prime movers, which drive the propulsion system.
Some examples of deepwater pipelines installed by the S-lay method from a dynamically positioned vessel (the Allseas ship Lorelay) are the 25-mile long, 14-inch gas and 12-inch oil export pipelines constructed from Shell Offshore Inc.'s Ram Powell tension leg platform at Viosca Knoll (VK) Block 956 to VK 817, and from VK 956 to Main Pass (MP) Block 289, respectively. The water depth along these routes ranges from 3,218 ft at VK 956 to 670 ft at VK 817 and 338 ft at MP 289. The Lorelay also installed three 6-inch gas pipelines in water approximately 5,400 ft deep between three subsea wells in Mississippi Canyon (MC) Block 687 and a subsea manifold in MC 685 (Shell's Mensa project).

J-Lay Method by Conventionally Moored Lay Barges

A comparatively new method for installing offshore pipelines in deeper water is the J-lay method. The method is so-named because the configuration of the pipe as it is being assembled resembles a "J." Lengths of line pipe are joined to each other by welding or other means while supported in a vertical or nearvertical position by a tower and, as more pipe lengths are added to the string, the string is lowered to the ocean floor. The J-lay method is inherently slower than the S-lay method and is therefore more costly.
The J-curve pipe-laying technique represents a logical extension of the industry's capability into deepwater. The J-lay method offers an alternative to the conventional lay barge in that the stinger requirements for deepwater are greatly reduced. The purpose of a stinger in the J-lay configurations is to change the angle at the top of the pipeline to a vertical orientation. The orientation of the pipeline at the surface does not have a large over-bend region and thus results in relatively small horizontal and vertical reactions on the stinger. The method is attractive as the bending stresses are low, the horizontal force required for stationkeeping is within the capability of dynamic positioning systems, and the use of modular towers allows derrick barges and moderately sized support vessels to be equipped for pipeline installations.
The maximum operating water depth in which a conventionally moored lay barge can operate is a function of its anchoring capabilities. Generally speaking, this is about 1,000 ft, and conventionally moored lay barges are not normally used for J-lay pipeline installations in this water depth because of the required tension on anchors and the pipe-bending stress. The J-lay method is difficult to use in water depths as shallow as 200 - 500 ft because of limited pipe angle and the bending stress imposed on the pipe.
The number of anchors used by a conventionally moored lay barge engaged in a J-lay operation is very similar to the number of anchors used by a conventionally moored lay barge engaged in an S-lay operation, which would be 8 to 12 anchors, depending on lay barge size. The relationship between the size of a vessel and the size of the anchors required for holding the vessel on-station is not a function of the pipeline installation method being used but, as previously discussed under the S-lay method, a function of the size of the lay barge. Stationkeeping requirements would be very similar to those required for a conventional lay barge using the S-lay method.
Similarly, the number of anchor relocations per mile of pipeline constructed is not a function of the installation method being used, but is related to the size of the lay barge, the water depth, and the amount of anchor line that can be stored, deployed, and retrieved by the lay barge. The number of anchor relocations per mile of pipeline installed by a conventionally moored lay barge employing the J-lay method would be very similar to the number of relocations required for a conventionally moored lay barge employing the S-lay method.
The number of anchor-handling vessels associated with a J-lay pipeline installation by a conventionally moored lay barge would be essentially the same as for a similar size barge using the S-lay method: from one vessel rated at 3,000 to 5,000 hp for a smaller lay barge operating in shallow water, to two vessels rated at 8,000 to 10,000 hp for a lay barge operating in 1,000 ft of water.

J-Lay Method by Dynamically Positioned Lay Barges

The minimum water depth at which dynamically positioned lay barges are believed to have an economic advantage over conventionally moored lay barges is estimated to be about 600 ft because the minimum radius of pipeline bend must be between 80� and 90� in 600 ft.
A dynamically positioned lay barge will typically consume more fuel and therefore emit more air pollutants per mile of pipeline installed than a conventionally moored lay barge. There are two other factors that help to equalize the differences in the air quality impacts: (1) conventionally moored lay barges typically require the assistance of other vessels to move from station to station and to deploy and recover anchors, and (2) dynamically positioned lay barges typically work in deeper water, that is, farther offshore and, therefore, have less potential to impact onshore air quality adversely.
Two examples of deepwater pipelines constructed by the J-lay method from a dynamically positioned installation vessel are the two 12-inch export lines that transport production from Shell Offshore Inc.'s tension leg platform (TLP), (Auger [2,850 ft of water in Garden Banks Block 426] [GB 426]), one a 71-mile-long oil line between GB 426 and Eugene Island Block 331 (water depth 243 ft), and the other, a 35-mile-long gas line between GB 426 and Vermilion Block 397 (water depth 380 ft). McDermott's dynamically positioned derrick barge DB 50, which had been outfitted with a portable J-lay, installed both lines. This vessel also installed 40 miles each of a 14-inch and an 18-inch pipeline to transport gas and oil, respectively, from Shell's Mars TLP at Mississippi Canyon Block 807 (in 2,950 ft of water) to West Delta Block 143 (in 369 ft of water).

Bottom-towed Pipeline

A less commonly used method of constructing offshore pipelines is the method of onshore fabrication whereby the pipeline assembly process, that is, the welding, inspection, joint-coating, and anode installation normally carried out on a lay barge immediately prior to the pipeline going into the water, is performed at a fabrication facility located onshore. The assembled pipe is then towed from the onshore location to its designated position by seagoing vessels. The pipeline is towed near the seafloor along a route that was presurveyed to identify any potential hazards. The assembled pipe can be towed either as an individual pipeline or as a bundle of several pipelines.
This method of installation is particularly well-suited to pipe-in-pipe flowline assemblies, which can be more efficiently fabricated onshore, and which have thermal insulation in the annular space between the inner and outer pipes. Such insulated pipe-in-pipe flowline assemblies are necessary to maintain the temperature of the produced fluids during transport through the very cold water of the deep Gulf of Mexico.
A limitation of this installation method is the increased risk that the pipeline could be damaged during the tow through contact with a subsea obstruction. Such damage could result in potentially catastrophic consequences if the integrity of the outer pipe were compromised, resulting in the exposure of the thermal insulation to the subsea environment.
An example of a pipeline installation using the bottom-tow method is BP Amoco's project that installed dual 10-inch oil pipelines during the summer and fall of 1997 between the subsea production manifold at their Troika Field development in Green Canyon (GC) Block 200 (GC 200) and the host platform, Shell Offshore Inc.'s Bullwinkle (GC 65, Platform A). The water depth along the route varies from 2,700 ft at GC 200 to approximately 1,400 ft at GC 65. The 10.75-inch outside diameter (O.D.) oil lines are encapsulated within a 3-inch thick shell of polyurethane foam insulation, and this assembly is installed within a 24-inch O.D. pipe; the annular space between the outer pipe and the foam insulation is filled with pressurized nitrogen. The pipelines were towed offshore from the fabrication facility on the Matagorda Peninsula on the Texas coast in four sections, each 7 miles long. The tow route used by BP Amoco followed parts of a route that Enserch Exploration, Inc., had previously surveyed and used for bottom-towing several pipelines installed between GB Block 388 and Eugene Island Block 315, and between Mississippi Canyon Block 441 and Ewing Bank Block 482.
Sumber: http://www.globalsecurity.org/military/systems/ship/offshore-pipelaying.htm